Current Projects  
 

ONGC - ICP-R PLATFORM


ICP-R

Oil and Natural Gas Corporation Limited (ONGC), India largest oil and gas company, awarded Gunanusa-AFCON Joint Venture to execute the ICP-R Process Platform Project in Mumbai High North, India.

The project scope of works is the Engineering, Procurement, Construction, Commissioning and Installation of the ICP-R platform, Flare Tripod and connecting bridge. The ICP-R platform consist Main Structural Frame, Building Module, Process Module, Turbo Generator and Compressor Module which has a weight of 7300 MT and the jacket weight is 3600 MT. The Flare Tripod topside weight is 90 MT and the jacket is 630 MT.The water depth is 75 m.

This is the first Gunanusa-AFCON Joint Venture project, and the installation was completed on April, 2011.


Main Support Frame (MSF) Load Out

Flare Tripod Installation, with ICP-R in the background

ICP-R Fabrication